| New
Lines |
No. |
Name
of Survey |
Approx
cost (in lakh) |
Year |
Physical
Progress |
| 1. |
Preliminary
Engineering cum traffic survey for New BG line between
Chinchwad-Roha. (95 kms) |
12.57 |
95-96 |
Field
detail survey completed. Consolidated estimate vetted
& report is finalised. |
| 2. |
RECT
survey for New line between Shirpur-Mhow (185 kms) |
12.49 |
00-01 |
Comments
from COM, Western railway are being called for. |
| 3. |
RECT
Survey for new line from Pandharpur – Lonand |
7.25 |
05-06 |
Traffic
Survey completed and Traffic report circulated to
all survey team on 20.12.05. Traffic chapter vetted
by FA & CAO(C) on 16.2.06. Field survey completed
for Pandharpur - Phalton section. Engineering details
received and the same are circulated to survey team
for preparation of their estimate. |
| 4. |
Upating
Traffic Survey for Wardha-Yavatmal-Pusad-Nanded New
BG line. |
2.08 |
05-06 |
Report
submitted to railway Board in August '06. |
| 5. |
Updating
traffic Survey for Kalyan-Ahmednagar via Murbad New
BG line (240 kms) |
7.20 |
06-07 |
Revised
Traffic Survey has been completed and under A/c vetting.
Updating cost is under A/c. vetting |
| 6. |
RECT
survey for New line between Veer-Harihareshwar (45
kms) |
3.03 |
06-07 |
Consolidated TOR is under finalisation
for approval of Railway Board. Survey Estimate has
been vetted on 26.03.2007. |
| 7. |
RECT
survey for New line between Karad - Chiplun (90 kms) |
6.08 |
07-08 |
TOR called from field units.
Survey Estimate sent to accounts for vetting on 24.04.2007. |